| |
This page is under construction!
The Implementation/Execution Phase of the Project
During the
Implementation Phase of a project you have to
-
Manage
a Team of People
-
Develop a
monitoring system to control schedule, resources, and expected outcome.
-
Demonstrate
evaluation and review techniques of cost management systems.
-
Manage
and Lead


1.24.1.D - Work Performance Information (WPI)
Work Performance Information is a primary input into controlling processes. WPI
is a general term for any and all information regarding the status of project
activities and deliverables and may include:
·
Start and end dates of completed schedule activities,
·
Start date, % complete and estimated completion dates of incomplete
activities,
·
Quality metrics of completed deliverables,
·
Actual and current estimated costs of completed and in-progress activities
and deliverables,
·
Resource utilization, and
·
And anything else you can think of.
1.25.0.D -- Manage and Control
Project Work
Earned Value Management (or Earned Value Technique):
Earned
Value Management (EVM) is a tool use in the Manage and Control Project Work
Process and is also known as Earned Value Technique. The concept of value to
the customer is expressed in work, time, and Cost. The work of the project
(deliverables) represents “value” to the buyer (customer, sponsor). Value is
determined at project start (budget). EVM assesses progress of deliverables
against the agreed to schedule and cost. The “formulas” are part of the PMP
Exam.

On chart: PV = BCWS and AC = ACWP
Budgeted At Completion (BAC)
(as used for the PMP):
BAC is derived
by looking at the total budget cost for the project and tells the PM the
original planned cost for this project.
Also known as BCAC or Budgeted Cost at Completion.
Example: The project is for 20
fast computers at $5,000 a computer. The BAC = 20 x $5,000.oo =
$100,000.oo.
Budgeted At
Completion (BAC), or Total
Project Budget, or Budgeted Cost at Completion (BCAC) = $100k
Planned Value (PV)
(as used for the PMP):
PV
tells the PM how much work should have been completed at
a point in time based on the plan. PV is the planned percentage complete
times (x) the BAC. PV is also know as BCWS or Budgeted Cost of Work
Scheduled.
Example: The project
plan was to have 14 computers completed by today which is 70% complete therefore
PV = 70% x $100,000.oo =
$70,000.oo.
Planned Value
(PV) or Budgeted Cost for Work Scheduled: BCWS = $70,000
Actual Cost (AC) (as used for the PMP):
AC tells the PM how much money has been spent
during a given period of time. AC is calculated by the sum of costs for
the given period of time. Also known as ACWP or Actual Cost of Work
Performed.
Example: The project has use 85% of the
funds available or $85,000. Therefore AC = $85,000.oo.
Actual Cost (AC)
or Actual
Cost for Work Performed (ACWP) = $85k
Earned Value (EV)
(as used for the PMP):
EV tells the PM how
much work was actually been completed during a given point in time. It is
derived by measuring where the project is in terms of work completed based on
the point in time on the schedule. Also know as BCWP or Budgeted Cost of
Work Performed.
Example: The project is
60% complete
(don't worry it is just pretend - 12 computers have been built) therefore EV =
60% x $100,000.oo =
$60,000.oo.
Earned
Value (EV) or Budgeted
Cost for Work Performed (BCWP) = $60,000.oo

On the chart: BAC = BCAC = $100K; AC = ACWP =
$85K;
EV =
BCWP = $60K; PV = BCWS = $70K
SV = $-10K; CV = $-25K
Three of the Types
of Variances Used in Earned Value Analysis:
Schedule Variance (SV) (as used for the PMP):
SV tells the PM the difference between where the plan says should be
and where we are in the schedule.
SV = EV - PV.
Example: The EV = $60K and the PV = $70K, Therefore the SV = $60K -
$70K = $-10K. Not good
(late is negative). Note, time is
measured in dollars.
Cost
Variance (CV)
(as used for the PMP):
CV
tells the PM the difference between what the plan say is should have
cost us and how much we actually spent.
CV = EV - AC.
Example: The EV = $60K and the AC = $85K, Therefore the CV = $60K -
$85K = $-25K. Not good
(late is an overrun). Note, this
time dollars is measured in dollars.
Performance Indices to Assess Project’s Progress:
Here variances
are also formulated as ratios rather than differences. Good when comparing
different projects.
Schedule
Performance Index
(SPI )
(as used for the PMP):
SPI
is the rate at which the project performance is meeting schedule
expectations at a point in time.
SPI = EV/PV
Example: The EV = $60K and the PV = $70K, therefore the SPI = 60/70 =
.86 (less than one is not good).
Cost
Performance Index (CPI)
(as used for the PMP):
CPI is the rate at which the project performance is meeting cost
expectations at a point in time.
CPI
= EV/AC
Example: The EV = $60K and the AC = $85K, therefore the SPI = 60/85 =
.71 (less than one is not good).
Cumulative CPI (CPI
C) (as used for the PMP):
The Cumulative CPI is the rate at which the project performance is meeting
cost expectations From the Beginning up to a point in time.
It is best
done with a table of all the measures over time (i.e., weekly/monthly).
It is also use to forecast project costs
at completion.
CPI
C =
Cumulative
EV /Cumulative
AC

On The Chart: EAC = FCAC; ETC = FCTC
Estimate At Completion (EAC)
(as used for the PMP):
EAC projects the total cost at completion based on project
performance up to a specific date.
EAC = BAC/Cumulative CPI .
Estimate To Completion (ETC)
(as used for the PMP).
ETC projects future spending on the
project based on past performance.
ETC = EAC - AC
Variance At Completion (VAC)
(as used for the PMP)
VAC is the difference between what was
budgeted and what will actually be spent.
VAC = BAC - EAC
Other Measures
-
Accounting Variance (AV) = PV - AC
-
STWP -
scheduled time for work performed
-
ATWP -
actual time of work performed
-
TPI (Time
Performance Index) = STWP / ATWP
Control Accounts:
Control
Accounts are management control points where scope, budget, actual cost and
schedule are integrated and compared to earned value for performance
measurement. It would take too much time and money to do Earned Value Analysis
for every work package. So only critical parts of the project WBS will be
monitored & controlled using EVA. The Control Account Plan (CAP) documents
places on the WBS where caps will be applied to scope, schedule, and budget
amounts on all of the WBS identified control points.

2.0 - Scope Management:
Scope Management includes project
as well as product scope. Poor scope management is a primary cause in project
schedule and budget overruns. Ensuring the project includes all the work and
only the work required to be successful. The project scope should be:
1.
Documented
2.
Well defined
3.
Clearly understood
4.
Achievable
Shortcuts in this knowledge area
are most dangerous therefore Project Managers must identify, validate, verify
scope and influence and control changes as they occur.
2.27.0.P Scope
Control
Performance
Reports
Performance Reports are the compilation, analysis, summarization & presentation
of project results and are outputs of Performance Reporting.
2.27.1.D -
New Project Work (NPW):
Additional work on the project may be a result of the following items. Each of
the following must be processed in the sequence below:
1.
Recommended
2.
Approved
3.
Implemented
Change Requests:
Are requests to modify the project (including product) scope, processes, plan,
policies, procedures, costs, budgets or schedule.
Corrective Action:
Any activity taken as a result of a variance from the PM Plan that will bring
future results in line with the plan.
Preventative Action:
Any activity that can reduce the probability of negative consequences associated
with project risks.
Defect Repair:
Activity resulting from identification of a defect in a project component.
Involves repair of the defect or replacement of the component.
The Concept of Triple Constraints:
There are three very important
parts to a project, Time, Cost, and Functionality. (or some say Scope or
Performance/Technology). Change to any one aspect will effect at least one
other (quality, customer satisfaction, or risk may also be effected). When
Scope is in question, do what is best for the customer with all other things
being equal. However, a good rule to follow may be this. If a
customer wants to change one constraint always control of the other two
constraints.

Harold
Kerzner, Project Management, A systems approach to Planning Scheduling and
Controlling, Seventh Edition, John Wiley & Sons, Inc. 2001

3.29.0.P - Schedule Control:
The Schedule Management Plan:
The Schedule Management Plan was
produced during the Develop Project Management Plan Process. It guides
execution of all time management processes and may include:
-
Network diagramming instructions
-
Rules
for dependency determination
-
Precision level required for duration estimates
-
Scheduling units (i.e. hours, days, weeks, etc.)
-
Process for managing schedule changes/updates Time
Schedule Change
Control System:
Procedures by which the project schedule may be changed including documentation,
tracking systems, and approval level.
Performance
Measurement:
Performance measures include using metrics such as SV and SPI to determine if
project is with acceptable performance tolerances. Helps identify variances
before they create major project impacts. Also go to see the seven steps to
performance measures.
Variance Analysis:
A variance is a deviation from the expected or planned event. The variance
analysis is comparing planned schedule dates vs. actual start and finish dates
and investigating the cause and impact of the deviation.
Progress
Reporting:
Providing information to project stakeholders should be presented in a
consistent format to facilitate periodic comparisons. The progress
reports will include measures such as:
·
Actual start/finish dates
·
Remaining duration
·
Percent complete
4.30.0.P -- Cost Control:
Performance Measurement Analysis:
Performance measurement analysis is a tool used in the Cost Control Process for
developing key values for monitoring and controlling each schedule activity,
work package or control account (e.g. PV, EV, AC, ETC, CV, SV, CPI, SPI). It
helps assess the magnitude of any variance. This is important for the project
manager must determine the cause of any variance.
Forecasting:
Forecasting is a tool of the Cost Control Process for making estimates or
predictions about the projects future based on information available at the time
of the forecast.
Project Performance Reviews
Project Performance Reviews are meetings to assess the progress of schedule
activities, work packages, or control accounts. The reviews often use variance
analysis, trend analysis or earned value techniques.
Cost Estimate
Updates:
Cost Estimate Updates are outputs of the Cost Control Process that explain any
change in cost information used to manage the project. Appropriate stakeholders
should be notified because some changes may drive adjustments to project scope,
schedule, quality, staffing.
Cost Baseline Updates:
Cost Baselines Updates are outputs of the Cost Control Process. Cost
Baselines are generally updated only in response to an approved changes
in project scope. For large variances may required rebaselining.



8.0 -- Communication Management:
The communication management knowledge area includes processes to address the
timely and appropriate generation, collection, distribution, storage, and
retrieval of project information. It includes communication with all
stakeholders (but especially project team, senior management, customer and
sponsor). Some say it is the most important skill for a PM to have. PM spend
up to 90% of their time communicating and therefore PMs must communicate:
-
Directly (always deal with the problem)
-
Truthfully (the whole truth)
-
Accurately (even if you don’t believe it)


From the words of Jerry Westbrook
"The Number One Enemy
of Good Quality
Are
the Words,
I Think and
I
Know."
-
Team
Problem Solving
-
Conflict
-
Designing Performance
Measures and Metrics
-
Reporting
PowerPoint Presentation (From Book)
Records Management and
Communications:
Communication Records web link Website Owner; Internal Revenue
Service
http://www.irs.gov/irm/part1/ch12s49.html,
This website explains
records management and descriptions and authorities for communication
records management.
Frank
Merrell, UoP 2005 |

Managing Change Discussion
Implementation (Execution) Phase
By Ulysses M.
Minor (MBA Student,
UoPhx, 2007)
Definition
The Implementation phase involves
executing the tasks outlined in the Planning phase.
As the phase unfolds, establishing control
methods that compare the planned and actual project
outcomes are necessary to ensure that the project
meets time, budget, and resource constraints.
The project manager must report the variances
found to the project team and stakeholders to
maintain project integrity.
Furthermore, the project manager must work
closely with all involved to design action plans
that address the variances so that the project can
maintain its scope or readily adapt to any
unpredicted scope changes.
A sample checklist that a project manager may
use to track a project during this phase follows:
Action Items:
Common PLC Project
Version 6.0
12-11-03
Item #
|
Description
|
Who
|
Date Assigned
|
Date Due
|
Status
|
Date Closed
|
1
|
Send Division1 process docs to Person1
|
(responsible person name here)
|
8-2
|
8-3
|
Done
|
8-3
|
2
|
Send email list for each location to Person1
|
|
8-2
|
8-3
|
Done
|
8-3
|
3
|
Send time/cost quote to Person3
|
|
8-2
|
8-6
|
Done
|
8-3
|
4
|
Set up email team distribution list
|
|
8-2
|
8-15
|
Done
|
10-28
|
5
|
Distribute materials for PDR
|
|
8-2
|
8-6
|
Done
|
8-6
|
6
|
Investigate electronic setup for PDR
|
|
8-2
|
8-7
|
Done
|
8-7
|
7
|
Schedule conference room for PDR
|
|
8-2
|
8-7
|
Done
|
8-7
|
8
|
Investigate cost of 11x17 PLC poster
printing, and big conference room poster
creation
|
|
8-2
|
8-17
|
$2 each in color for 11x17; $200+ for 4x3
foam-board
|
8-17
|
9
|
Revisit DDR dates - make sure not too
aggressive for proper Division2 review
|
|
8-2
|
8-8
|
DONE. See updated project plan- now 8-20
|
8-8
|
10
|
Talk to Pubs about needs, staff
availability, recommend how to handle binder
creation
|
|
8-2
|
Now
9-12
|
Done- Person1 doing updates
|
10-5
|
11
|
Decide offline how want to deploy PLC in
Division3 as relates to cross functional
groups.
|
|
8-2
|
9-15
|
Person3: has Div3 conceptual buy-in, wants
them to review QuickRef
|
11-08
|
12
|
Add someone from Mfg to team list and
distribution
|
|
8-2
|
8-24
|
Done
|
8-24
|
13
|
Consider a special mtg to walk
cross-functional reps through PLC framework
|
|
8-2
|
8-14
|
Decision: groups will handle as part of
deployment
|
8-20
upd 9-5
|
14.
|
Distribute draft of "cheat sheets" for
different types of projects
|
|
8-8-01
|
8-15-01
|
Done
|
8-17-01
|
Item #
|
Description
|
Who
|
Date Assigned
|
Date Due
|
Status
|
Date Closed
|
15.
|
Make sure cheat sheets and minimum
deliverables lists, etc. incorporate "best
practices" as called for in our Vision.
Reference lessons learned meeting
|
(responsible
person name here)
|
8-22
|
8-29
|
Done
|
8-29
|
16.
|
Decide how many conference room wall boards
we'll create
|
|
8-20
|
9-5
|
Done – send them the file, they will make
their own
|
9-5
|
17
|
Email approval of final Quick Ref (received
9-12), or send email ASAP if another review
meeting is needed
|
|
9-5
|
9-14-01
|
Done
|
9-28
|
18
|
As part of deployment for Div3-- get binders
made up for software and hardware groups
|
|
11-13
|
In time for courses in Div3, to be scheduled
|
First run made by 11-20 for software PLC
class. Second run completed 12-12 for
hardware PLC course. To be distributed by
12-14
|
12-12
|
19
|
Send Div2 the electronic PLC Files or let
them know where to get it online.
|
|
11-13
|
12-17
|
|
|
(Table from
www.projectconnections.com, 2006, p.1).
Implementation
Project
Monitoring System
Much of the success a project may enjoy
does not lie in executing the tasks, but in
monitoring the effect that the executed tasks yield.
An effective project monitoring system helps
the Implementation phase achieve its maximum
potential.
Gray and Larson contend, “A project
monitoring system involves determining what data to
collect; how, when and who will collect the data;
analysis of the data; and reporting current
progress” (Gray and Larson, 2005, p.411).
Metrics set by the project team determines
data collection.
The team should design a system or use a
software package that helps collect and analyze this
data.
In terms of reporting, the following format
addresses the major reporting concerns of this
phase:
§
Progress since last
report
§
Current status of
project
o
Schedule
o
Cost
o
Scope
§
Cumulative Trends
§
Problems and issues
since last report
o
Actions and
resolutions of earlier problems
o
New variances and
problems identified
§
Corrective action
planned (Gray and Larson, 2005, p.412).
If the team masters this
system, the project control process becomes easier
and more visible.
Project
Control Process
Project Control Process (PCP) is the act of
evaluating actual project performance against the
set plan to find deviations, evaluate alternate
action courses, and implement the corrective action.
This process involves the following steps:
-
Setting a Baseline Plan-
Setting a baseline plan gives the blueprint of
the project and yields a reference point.
The cost and duration information in the
work breakdown structure (WBS) comprises this
plan.
-
Measuring Progress and
Performance- This objective measures time,
budget and resources.
Using the Earned Value System gives
substance to this objective.
-
Comparing Plan against
Actual- The most important function of this
objective is to allow enough time between
reports to detect variances that may change the
course of the project.
-
Taking Action- Reacting to
variances sometimes resulting in changing the
scope of baseline plan (Gray and Larson, 2005,
p.413).
Using the
Earned Value System
So far, the systems introduced to monitor
time and budget are functional yet cannot yield
their full potential without integration.
The Earned Value System (EVS), developed by
the U.S. Department of Defense, attempts to overcome
the ineffectiveness of using non-integrated systems
to monitor progress.
Gray and Larson contend, “Without
time-phasing of costs to match scheduled activities,
cost control cannot yield information that is
reliable for control purposes” (Gray and Larson,
2005, p.417).
The project budget baseline, which consists
of the time-phased costs, gives the EVS its starting
point, the planned value (PV).
This information can help the project manager
make comparisons between actual and planned schedule
using the notion of earned value.
Data derived from the WBS, project network
and schedule provides the bulk of the information
used by the system.
As a result, the system produces cost and
schedule variances, which is useful for determining
project outcome and status.
Using this system affords the project manager
the flexibility of monitoring the project at any
time, which gives the entire project agility and
momentum.
The driving force behind the EVS is the
Percent Complete Rule.
This rule assigns costs to the baseline and
establishes milestones across the work package, then
attaches completion percentages in dollars (Gray and
Larson, 2005, p.421).
For instance, a factory measures progress by
each a box of goods processed at a rate of $10 in
labor per box.
At the end of the day, the factory manager
can determine labor and production by either looking
at boxes produced or by the labor dollars used.
Then, the manager compares the actual results
to the planned budget and makes any necessary
adjustments.
Analyzing
Variances
A project manager must understand the
variances in order to take action.
Positive variances mean that the project is
going well, while negative variances indicate
problems.
Determining variance involves comparing
earned value with schedule value, and comparing
earned with actual costs.
The schedule and cost variances (SV and CV)
can be determined by assessing planned cost (PV),
budgeted cost of completed work (EV), and actual
cost of work completed (AC).
CV shows whether costs exceeded
or fell short of planned costs.
SV indicates the progress of the work
packages in WBS in relation to their scheduled
dates.
Dollars are the SV unit instead of time (Gray and
Larson, 2005, p.421).
Project managers must ensure that the SV does
not determine the timeliness of the critical path.
Only comparing planned and actual schedules
makes this determination.
In addition, using Cost Performance Index
(CPI = EV/AC) and Scheduling Performance Index (SPI
= EV/PV) determine the efficiency for each element.
Relation to
the Project
According to Donald Geigrich, using project
control helps to identify precursors to following
items that impact cost, schedule and quality on a
construction project:
-
Delays and Schedule
Changes
-
Design difficulties
-
Payment irregularities
-
Scope changes
-
Unsatisfactory quality of
work
-
Slow completion of work
-
Owner actions
-
Performance of project
personnel
-
Lack of teamwork
-
Disputes and claims
(Geigrich, 2002, p.2.1)
The most threatening of these
is scope changes.
The year 2007 will see building materials
cost, other than lumber, rise 6 to 8 percent, which
economist believe to be twice the rate of inflation
(www.kansas.com,
2007, p.5).
Through 2006, the price increase for these
materials caused many industries to halt or trim
down the scope of their construction projects (www.alaskanjournal.com,
2007, p.9).
However, managing the execution phase using
the tenets described above will help create a
strategy to decrease the likelihood of major scope
changes caused by unforeseen conditions such as
price increases in mid-project.
Summary
The Implementation phase carries out the
objectives outlined in the Planning phase.
Creating an Integrated Project Monitoring
System helps the project manager monitor time and
resources used, and report the findings to the team
and stakeholders. Using the Earned Value System
helps identify variances between the actual and
scheduled plans.
Finally, analyzing the variances and taking
action helps reduce the likelihood of making major
changes to the project scope.
References
Giegerich, D. B. (2002). Early
warning signs of troubled projects.
Transactions
of AACE
International, 02.
Gray, C.F. and Larson, E.W.
(2005).
Project Management:
The Managerial Process.
3rd
Ed.
McGraw-Hill.
www.alaskanjournal.com. (2007).
Construction spending predicted to jump to
$7B in
’07.
Retrieved February 24, 2007 from
http://www.alaskajournal.com/stories/021107/hom_20070211005.shtml.
www.kansas.com.
(2007).
Lumber costs fall; other building materials rise.
Retrieved
February 24, 2007 from
http://www.kansas.com/mld/kansas/business/16467881.htm.
www.projectconnections.com (2007).
Execution phase checklist.
Retrieved February 24,
2007 from
www.projectconnections.com.
Implementation Phase
Tasha Palmer (MBA Student, UoPhx
2007)
After the planning phase is
complete, the team is ready to start implementing
their project.
Implementing their project refers to the
final process of moving the solution from
development status to production status (www.lifecyclestep.com).
This is where the project is developed and
where the team will spend most of their time.
One of the most important things in the
implementation phase is discipline.
Discipline is important in executing the
tasks from the planning phase.
Without discipline, it is difficult to stay
on schedule and within budget.
In order for the team to be
successful in implementing their project, the
project must identify four critical processes.
The processes are change management, risk
management, performance measures, and a phase
review.
Each process is important in order to achieve the
outcome desired.
Change
management is important because of the many
changes that occur in the business environment.
By having an effective change management
process, the manager can decrease the impact of any
changes, identify risks due to change, and control
the costs.
The team can accomplish all of these things
by following the processes of change management.
Process 1: Identify Change
The first step to making changes
is identifying what they are.
Once the project manager identifies the
changes, a team member will record and describe the
impacts of the change.
Process 2: Review Change
This step consists of reviewing
the impact and identifying the reason for change.
While reviewing, the project manager will
determine if the change will affect the delivery of
the project.
If so, the project manager will have to seek
approval to make the changes.
Process 3: Approve Change
During this step, the project
board determines whether the team should move
forward.
They make the decision based on the level of risk,
impact, benefits, and costs that the change has on
the project (www.method123.com
).
Process 4: Implement Change
In the last step of change, the
project manager approves and changes and the project
continues.
After implementing the change, the manager
will evaluate the effects the change had on the
project.
They want to make sure that they achieved their
desired outcome.
Risk
Management is important because it helps us find
ways to manage events that will negatively affect
the financial, physical, or human capital of an
organization (www.army.mil).
Risk management can prevent business risks
such as:
-
financial risks
-
process risks
-
time risks
-
human risks (loss of a
knowledgeable and skilled individual)
-
legal risks or
-
physical risks (loss of
equipment), etc (
www.army.mil )
In order to prevent these risks,
it is imperative to develop good prevention
strategies.
A good strategy will prevent or minimize the
impact it will have on a project.
Performance
Measures give life to the mission, vision, and
strategy by providing a focus that lets each
employee know how they contribute to the success of
the company and its stakeholders’ measurable
expectations (Artley, Stroh, 2002).
It develops
measurable indicators to track and evaluate progress
in achieving goals, providing feedback, and gaining
insight to management. One the measurable indicators
that project managers use is the monitoring system.
The monitoring system will help the manager
track their team’s progress.
They will be able to determine the:
-
Effectiveness- Is the team
doing the right things?
-
Efficiency- Is the team doing
thing correctly?
-
Quality- Is the team meeting
the standards?
-
Timeliness- Is the project on
schedule?
-
Productivity- Is the team
being productive in their tasks?
By using these performance
measures, the project manager will know how well the
project is going, if they are meeting their goals,
if improvements are necessary, etc.
Not only are performance measures important,
but the communication of them are critical.
It is important for the project manager to
inform their team on their expectations.
They can accomplish by having a meeting, a
conference call, through email, etc.
Whatever it takes to get the job done, they
should do.
Performance measures are an asset to a
project.
They keep everyone focused on accomplishing the task
Phase Review ensures that all of
the required tasks are complete.
After the review, the project manager will
determine if the project is ready to close.
If the team completes the above steps, then
their chances of achieving a successful project
delivery are high.
References:
www.lifecyclestep.com (2003-2005).
Implement.
Retrieved on February 26, 2007 from
http://www.lifecyclestep.com/open/450.0Implementation.htm
www.method123.com (2006).
Performing Change Management.
Retrieved on February
27, 2007 from
http://www.method123.com/articles/2006/12/11/ChangeManagement/
www.army.mil (2007).
Risk Mitigation.
Retrieved on February 28, 2007 from
http://www.army.mil/armybtkc/focus/cpi/risk.htm
Artley, Will, Stroh, Suzanne
(2001).
Establishing an Integrated Performance Measurement
System, The
Performance-Based Management Handbook.
Vol.2,
pg. 1
|
| |
|